Case study

Six Heritage was commissioned by Willmott Dixon to undertake a detailed condition survey of the north elevation of the Sherrington Building, a multi-storey laboratory building within the University of Oxford Science Area.

The investigation combined ground- and roof-level inspection with drone photography and laboratory analysis of the existing mortar. It established the condition of the brickwork, pointing, concrete copings and associated façade elements, identifying the causes of movement within the high-level parapet and developing a practical strategy for repair.

Author

Matthew Amis

Service

Façade condition survey

Completion

March 2026

Client

Willmott Dixon

Sherrington Building, Oxford
Sherrington Building, Oxford

The Sherrington Building is a mid-20th-century institutional building facing north towards University Parks. Its largely planar brick façade is arranged over several storeys, with repetitive window openings, a continuous parapet and a mixture of original and later elements, including replacement windows and external services.

The façade was divided into five areas to allow defects and repair recommendations to be recorded accurately. Inspection was undertaken from ground and roof level using analogue and digital survey techniques, supported by detailed drone photography of the elevation, parapet and adjacent roof surfaces.

Brickwork across the principal elevation was generally found to be in reasonable to good condition, with most of the masonry remaining sound and well bonded. Mortar joints were also largely intact and serviceable, although localised areas of washed-out pointing and mortar loss were identified, particularly at high level and around the ground-wall junction.

Minor damage to individual bricks had resulted from historic fixings, service penetrations and scaffold anchors. Localised staining and biological growth were also recorded beneath windows and sills, reflecting patterns of rainwater runoff and inefficient water shedding.

The principal concern was the condition of the high-level parapet. Sections of masonry exhibited stepped cracking, localised outward bulging and misalignment, with the severity varying along the elevation.

The pattern of deterioration was consistent with prolonged moisture penetration through defective coping joints and parapet masonry. Once within the wall, moisture had created conditions in which embedded ferrous elements could corrode. As iron and steel corrode, their volume increases, exerting considerable pressure on the surrounding masonry in a process commonly known as rust-jacking.

Two docked steel I-beams were present within the central parapet and were considered particularly relevant to the observed cracking and displacement. Smaller ferrous fixings distributed across the façade also presented a risk of future expansion-related damage.

A visible southward lean was recorded at the western end of the parapet. Although associated cracking was not observed in this location, the distortion was considered sufficiently significant to require further assessment by a structural engineer.

The pre-cast concrete coping units were generally weathered and affected by biological growth. Mortar joints between the units had failed extensively, leaving open pathways through which water could enter the parapet below. These defects were considered a significant contributor to the deterioration of the high-level brickwork.

Sherrington Building, Oxford

We recommended that high-level water ingress be addressed as a priority through the inspection and repair of roof finishes, rainwater goods, parapet drainage and coping details.

Once scaffolding has been erected, areas of cracked or bulging parapet masonry should be opened up under the direction of a structural engineer. Localised sections may require careful dismantling and rebuilding, particularly within the central areas of the façade where the most significant failures were identified.

Opening-up works should expose the embedded I-beams and other ferrous components so that their condition can be established. Corroded metalwork should be treated, isolated or replaced as appropriate, while redundant elements should be removed. Where new restraint or reinforcement is required, stainless-steel components should be used to reduce the risk of recurring corrosion.

Rebuilt sections should incorporate suitable movement provision and improved weathering details. Existing cracks should also be monitored using tell-tales at an early stage so that active movement can be distinguished from historic settlement or thermal cracking.

Outside the parapet, most of the brickwork was considered suitable for retention. Approximately 70–110 individual bricks may require localised repair or replacement, although repair mortar should be used where appropriate to avoid unnecessary removal of sound fabric. Any replacement bricks should match the originals in size, colour, texture and appearance.

Approximately 115 square metres of localised repointing was provisionally identified. Wholesale repointing was not considered necessary, but further defective areas may become apparent once close scaffold access is available.

All coping joints should be inspected and extensively repointed if the existing units are retained. The joints should be carefully compacted and finished to encourage effective water shedding, with the final mortar specification and joint profile confirmed through site trials.

The high-level decorative cartouche was found to be in moderate condition and suitable for retention. However, mortar loss around much of its perimeter had increased its vulnerability to water penetration. Close inspection from scaffolding should establish the condition of its concealed fixings, followed by localised repointing, minor repair and light cleaning as required.

Selecting a compatible repair mortar requires a balance between matching the existing construction and improving its long-term performance. Replicating the original cement-rich mortar too closely could perpetuate low permeability and concentrate stress within the bricks. Conversely, a mortar that is excessively soft may be unsuitable for the building’s exposure and construction.

A slightly weaker and more permeable cement-lime or hydraulic lime-based mortar may therefore be appropriate, subject to trials. The final mix should be compatible with the existing bricks in strength, colour, texture and permeability while remaining sufficiently durable for the exposed conditions.

Existing movement joints should be inspected, cleaned and resealed using an appropriate flexible system. This will allow the masonry to accommodate thermal movement while preventing the joints from becoming routes for further water ingress.

The established appearance and natural weathering of the façade should be retained wherever possible. Where cleaning is necessary to address biological staining, atmospheric soiling or salt deposits, low-pressure steam cleaning or a similarly non-destructive system should be trialled. Approximately 132.8 square metres of masonry exhibited some degree of soiling, but cleaning should remain targeted rather than universal.

Abrasive methods, high-pressure washing and aggressive chemicals should be avoided, as these could damage the brick faces and accelerate the deterioration of mortar joints.

The recommended repairs combine localised structural intervention with improvements to water management and material compatibility. By addressing defective copings, corroding metalwork and trapped moisture together, the work can preserve the substantial amount of sound original masonry while reducing the likelihood of recurrent movement and deterioration.

Context and materials – Understanding post-war brick masonry

Although the Sherrington Building is not individually listed, it lies within Oxford’s Central Conservation Area, encompassing the historic city and university. Its north elevation is visible from University Parks and forms part of the wider architectural character of the University Science Area.

The building represents a different conservation challenge from a traditional lime-built historic structure. Its mid-20th-century façade was constructed using load-bearing brick masonry and comparatively strong cementitious mortar, reflecting the materials and construction practices of the post-war period.

Laboratory analysis established that the existing mortar comprised Portland cement and sand in approximate proportions of 1:2.2 by volume. This is a dense, cement-rich mix, stronger than conventional standard specifications and substantially less permeable than traditional lime mortar.

While this construction is generally robust, its hardness can restrict the accommodation of thermal or structural movement. Dense mortar also limits the evaporation of moisture through the joints. Where water enters through failed copings or poorly sealed movement joints, it can consequently become trapped within the masonry.

These characteristics were particularly relevant at parapet level, where exposure is greatest and the wall is vulnerable from several directions. Moisture penetration, restricted evaporation and the presence of embedded steel had combined to produce cracking and outward displacement, despite the generally good condition of the remainder of the façade.